Chapter 10 · Section 10.8 of 8
Decommissioning, local content and the 2027 Petroleum Law: the decommissioning plan and fund, carrying out decommissioning, training and employment of Vietnamese staff, Vietnamese goods and services, domestic sales, safety, environment and insurance, the transition to Law No. 10/2026/QH16 on 1 March 2027 and what it may mean for existing contracts, and the overlap with offshore wind and carbon capture
What you need to know
- A contractor must prepare a decommissioning plan for approval and, within one year of first commercial production, set up a decommissioning fund, paid annually to Petrovietnam in proportion to participating interests and treated as a recoverable cost; shortfalls are topped up and surpluses returned (Articles 50 and 51, Law No. 12/2022/QH15; Articles 51 to 55, Decree No. 45/2023/ND-CP).
- Petrovietnam deposits unused fund money with a commercial bank in which the State holds a controlling stake, and interest is added to the fund; contributions must be completed before the contract or the field's production phase ends (Article 51).
- The contract must contain commitments on training, a research fund and priority for Vietnamese labour and services, and the contractor must transfer technology, train and employ Vietnamese workers and select suppliers competitively, reporting to Petrovietnam (Articles 30 and 59(3) and (12)).
- When the Government so requires, the contractor must sell its share of gas and its crude, at internationally competitive prices, in the Vietnamese market (Article 59(8)).
- Law No. 10/2026/QH16 replaces Law No. 12/2022/QH15 on 1 March 2027, adding post-closure responsibilities, carbon capture and storage, shared infrastructure and offshore energy linked to petroleum operations; MOIT has stated that the law respects the principle of non-retroactivity, but the transitional treatment of existing contracts should be confirmed in its text and decree.
Why decommissioning is front-loaded
Vietnam's producing fields are ageing. Many offshore installations in the Cuu Long and Nam Con Son basins were built in the 1980s and 1990s, and several fields are approaching or past the end of their original contracts. The State's concern is that the cost of removing platforms, plugging wells and restoring the seabed should not fall on the budget if a contractor leaves or fails. The 2022 law answers that concern by requiring decommissioning to be planned early and funded during production, through a fund the State party holds, rather than left to the contractor's balance sheet at the end of field life (FAQ 114).
The decommissioning plan
Article 50 of Law No. 12/2022/QH15 requires the contractor to prepare a decommissioning plan for the facilities in the contract area, which is appraised and approved by MOIT, with Petrovietnam's involvement; under Government Resolution No. 66.6/2025/NQ-CP some approvals of this kind are delegated to PVN until 28 February 2027. The plan must be submitted through PVN within one year of first commercial production and updated at least a year before the contract or the field's production ends (FAQ 114). Article 51 of Decree No. 45/2023/ND-CP governs the preparation and content of the plan, which in practice identifies the facilities to be removed, the methods, the timetable, the estimated cost and the environmental and safety measures.
The plan need not require full removal of every structure. Article 55 of the decree allows the authority to approve leaving facilities in place, deferring decommissioning, or carrying it out in part or in full, where the conditions in the decree are met; reuse of a platform for a new development or, in future, for a carbon storage project is the kind of case in which partial removal or deferral may be sought. A decision to leave facilities in place transfers continuing responsibilities, and the post-closure responsibilities introduced by the 2027 law are likely to bear on those decisions.
The decommissioning fund
Article 51 of the law requires the contractor to set up a fund to secure the decommissioning obligation within one year of the first commercial production of oil or gas from the contract area. Contributions are made annually, on the basis of the approved decommissioning plan, and paid to Petrovietnam, which manages the fund; each contractor contributes in proportion to its participating interest, and the contributions are recoverable costs under the contract. Contributions must be completed before the contract or the field's production phase ends. While the money is not used, Petrovietnam deposits it with a commercial bank in which the State holds a controlling stake, and the interest, after related financial obligations, is added to the fund.
If the fund is insufficient when decommissioning takes place, the contractors must contribute the shortfall; if there is a surplus after decommissioning is complete, it is returned to the contract parties as the contract provides. Articles 52 to 54 of Decree No. 45/2023/ND-CP govern the calculation of contributions, the management and use of the fund and its final settlement. Because contributions are recoverable, they are effectively funded out of production, and they reduce profit petroleum in the years they are made; because they are tied to the plan's cost estimate, an updated plan with a higher estimate increases the annual contribution.
Carrying out decommissioning
Article 52 of the law requires decommissioning to be carried out in accordance with the approved plan when the contract ends, when a field's production ends, or when facilities are no longer needed, and Article 59(7) makes clearing petroleum facilities, equipment and vessels a contractor obligation. The fund pays for the approved work. Where the contractor's term ends and Petrovietnam or another entity takes over the field under Article 41, the decommissioning obligation and the fund follow the facilities, and the handover agreement should settle who bears which liabilities, including for wells already plugged and for facilities left in place.
A buyer of a participating interest in a producing field inherits its share of the decommissioning obligation. Due diligence should cover the approved plan and its latest cost estimate, the fund balance, the contributions made by each party, any disputes about the estimate, and the contractual allocation of decommissioning liability between seller and buyer, which Vietnamese law leaves to the parties provided the obligation to the State is met.
Local content: training, labour, services and technology
Vietnam's local-content regime is principally contractual. Article 30 requires every petroleum contract to contain commitments on training, a research fund and the priority use of Vietnamese labour and services, and those commitments are bid variables in a licensing round. Article 59(3) obliges the contractor to transfer technology, train and employ Vietnamese workers and protect their lawful rights, and Article 59(12) requires the contractor to select suppliers of petroleum services and goods through competitive, fair, transparent and efficient processes consistent with the contract and to report the selection to Petrovietnam (FAQ 114). In practice, Petrovietnam's own service subsidiaries, in drilling, technical services, construction and shipping, compete strongly for contracts, and an operator must show PVN that its procurement complied with the contract.
Foreign specialists are employed under the ordinary work permit rules, which permit exemptions and simplified procedures in some cases (Work permits for foreign staff), and the operator's Vietnamese employees are covered by the Labour Code, social insurance and the operator's internal labour rules (Chapter 4). Technology transfer to Vietnamese parties may need registration under the technology transfer law (Technology transfer and licensing).
Domestic sales, safety, environment and insurance
Article 59(8) requires the contractor, when the Government so requires, to sell its share of natural gas under gas development projects in the Vietnamese market as agreed, and to sell its share of crude in Vietnam at internationally competitive prices. Domestic refineries and gas-fired power plants depend on that obligation, and gas sales agreements are negotiated against it. Article 59(10) requires the contractor to share existing infrastructure with third parties under agreement where this does not disrupt its operations, and Article 59(11) to allow other resource activities in the contract area that do not hinder petroleum operations.
Safety is governed by Article 8 of the law and Chapter V of Decree No. 45/2023/ND-CP (Articles 39 to 44), which govern safety management, risk assessment and emergency response for petroleum facilities under MOIT's supervision. Article 49 restricts flaring and venting of gas. Environmental impact assessments for field developments and environmental licences for operations are required under Law No. 72/2020/QH14, and contractors must maintain oil spill response capability under the Prime Minister's regulations on oil spill response. Insurance of facilities, wells, pollution and third-party liability is dealt with in the petroleum contract and the operator's insurance programme under Vietnamese insurance law; the coverage required should be checked against the specific contract, and placement through or alongside Vietnamese insurers may be required.
The transition to Law No. 10/2026/QH16
Law No. 10/2026/QH16 on Petroleum takes effect on 1 March 2027 and replaces Law No. 12/2022/QH15. MOIT's public statements in September 2026 describe five core changes: greater decentralisation to the State management authority and delegation of powers to Petrovietnam, with simplified procedures and stronger supervision, while powers relating to defence, security and force majeure stay with the competent authorities; additional incentives for small and marginal fields and for deepwater and far-offshore projects, and encouragement of enhanced recovery and tail-end production; a framework for carbon capture and storage, offshore energy and high-technology services linked to petroleum operations, including shared infrastructure; more flexible contracts that protect contractors' interests and allow the contract term to be extended and work commitments adjusted, with rules on how Petrovietnam's costs are treated where it performs obligations for the State; and accounting, audit and cost settlement rules aligned with international practice. Reports of the law also mention provisions on carbon credits and post-closure responsibilities.
What the law means for existing contracts depends on its transitional provisions and the implementing decree, which MOIT circulated in draft in 2026 for adoption by 1 March 2027. MOIT has said that the law observes the principle of non-retroactivity, which ordinarily means that contracts approved and signed under the 2022 law, and their fiscal terms, continue to apply, while procedures carried out after 1 March 2027, such as approvals of plans, amendments, extensions and transfers, follow the new law. Whether existing contractors can opt into the new incentives, and how pending applications are treated, should be confirmed against the final text before relying on any assumption. Contractors negotiating extensions or new contracts in late 2026 should consider whether to conclude them before or after the change.
Offshore wind and carbon capture: where the regimes meet
Two new activities will share Vietnam's offshore with petroleum. Offshore wind is electricity generation governed by Law No. 61/2024/QH15 on Electricity, which took effect on 1 February 2025 and contains specific provisions on offshore wind, together with the marine and investment laws on the use of sea areas (FAQ 93). The 2027 Petroleum Law's provisions on offshore energy concern facilities and infrastructure linked to petroleum operations, not offshore wind as such, so a wind project remains subject to the electricity regime even where it uses a petroleum platform or pipeline corridor. Conflicts over sea areas between wind and petroleum blocks are resolved through marine spatial planning and the approvals of the competent authorities.
Carbon capture and storage has had no specific legal framework in Vietnam. Law No. 10/2026/QH16 introduces rules on the location of carbon capture, the responsibilities of those who capture and store carbon, shared use of infrastructure and safety, limited to activities directly connected with petroleum operations, such as reinjection of carbon dioxide into depleted reservoirs. Its detail will be in the implementing decree. An investor considering CCS in a Vietnamese field should treat the framework as new and untested and should expect the allocation of long-term storage liability, and its link with decommissioning and post-closure responsibilities, to be the central question.
Preparing for 1 March 2027
Steps a contractor, or an investor in a petroleum contract, should take before Law No. 10/2026/QH16 takes effect.
- Map pending approvalsList plans, amendments, extensions and transfers that will be decided after 1 March 2027, and identify which authority will decide them under the new law and decree.
- Review contract terms against the new incentivesAssess whether marginal, deepwater or far-offshore fields could qualify for the new incentives and whether an amendment or a new contract would be needed to obtain them.
- Check the decommissioning positionUpdate the decommissioning plan and cost estimate; reconcile the fund balance; consider the effect of post-closure responsibilities on facilities left in place.
- Track delegated approvalsNote that the delegation of certain MOIT approvals to PVN under Resolution No. 66.6/2025/NQ-CP ends on 28 February 2027.
- Plan farm-ins and exitsDecide whether a transfer should be approved before or after the change, given the approval chain and any new conditions.
- Assess CCS and shared infrastructureIdentify depleted reservoirs, platforms or pipelines that could be used for carbon storage or shared with third parties under the new rules.
- Refresh local content plansConfirm training, research fund and procurement reporting against the contract and any new requirements in the decree.
Key obligations now and the 2027 direction of travel
| Topic | Under Law No. 12/2022/QH15 (to 28 February 2027) | Under Law No. 10/2026/QH16 (from 1 March 2027, as reported) |
|---|---|---|
| Approval of contracts and transfers | Prime Minister, on MOIT's appraisal (Articles 26 and 36) | Greater decentralisation to the State management authority and PVN; defence and security matters reserved; detail in the text and decree |
| Decommissioning | Plan approved by MOIT; fund paid annually to PVN within one year of first production; recoverable (Articles 50 to 52) | Carried over, with post-closure responsibilities added |
| Incentives | Incentivised and specially incentivised blocks on the Prime Minister's list (Articles 53 and 54) | Additional incentives for small, marginal, deepwater and far-offshore fields; enhanced recovery and tail-end production |
| Contract flexibility | Extensions of up to five years with MOIT approval (Article 31) | Extensions of term and adjustments of work commitments made easier |
| Carbon capture and storage | No specific framework | Framework for CCS linked to petroleum operations; carbon credits |
| Shared infrastructure and offshore energy | Contractor must share infrastructure by agreement (Article 59(10)) | Rules on shared use and offshore energy linked to petroleum operations |
| Accounting and cost settlement | Articles 56 and 57; Appendix B of Decree No. 45/2023/ND-CP | Aligned with international practice; new decree |
| Local content | Contract commitments on training, research fund, Vietnamese labour and services (Articles 30 and 59) | Expected to continue; check the new decree |
Worked example
Funding decommissioning for a mid-life oil field
A three-party contractor group (operator 50%, a Japanese partner 30%, Petrovietnam's subsidiary 20%) started commercial production in March 2025 and has an approved decommissioning plan with an estimated cost of USD 240 million. The production phase is expected to end in 2040. The figures and the contribution profile are illustrative; the actual method follows Decree No. 45/2023/ND-CP and the contract.
| Deadline to set up the fund | Within one year of first commercial production: by March 2026 (Article 51). |
|---|---|
| Contribution period | Annual contributions from 2026 to 2039, completed before the production phase ends. |
| Annual contribution (straight-line illustration) | USD 240 million over 14 years = about USD 17.1 million a year, before interest credited to the fund. |
| Shares | Operator about USD 8.6 million, Japanese partner about USD 5.1 million, PVN subsidiary about USD 3.4 million a year. |
| Cost recovery | Contributions are recoverable costs, recovered within the cost recovery cap, so they reduce profit oil in each year of contribution. |
| Updated plan in 2032 | Estimate rises to USD 300 million; remaining contributions are recalculated to close the gap by 2039. |
| Decommissioning in 2040 to 2042 | Work carried out under the approved plan; actual cost USD 285 million; surplus of USD 15 million plus accrued interest returned to the contract parties as the contract provides. |
| If the Japanese partner sells in 2030 | The buyer takes over the 30% share of the obligation and of the contributions already made; the farm-in agreement allocates any shortfall attributable to the period before completion. |
Had the field been handed to Petrovietnam at contract expiry under Article 41, the fund and the decommissioning obligation would have followed the facilities, and the handover agreement would have settled residual liabilities.
Had part of the facilities been approved to remain in place for a carbon storage project, the plan and the fund would have been adjusted under Article 55 of the decree, and the post-closure responsibilities under the 2027 law would need to be addressed.
Questions investors ask about decommissioning, local content and the 2027 law
When must a decommissioning fund be set up for a Vietnamese oil field?
Within one year of the first commercial production of oil or gas from the contract area, under Article 51 of Law No. 12/2022/QH15. Contributions are paid annually to Petrovietnam in proportion to participating interests, based on the approved plan, are recoverable costs, and must be completed before the contract or the field's production phase ends.
What happens if the decommissioning fund is too small or too large?
If the fund is insufficient when decommissioning is carried out, the contractors must contribute the shortfall. If money remains after decommissioning is complete, the surplus is returned to the contract parties as the contract provides. Unused money is deposited with a State-controlled commercial bank and interest is added to the fund.
What local-content obligations does a petroleum contractor have?
The contract must contain commitments on training, a research fund and priority for Vietnamese labour and services under Article 30. The contractor must transfer technology, train and employ Vietnamese workers, select suppliers competitively and report to Petrovietnam under Article 59, and sell gas and crude domestically when the Government requires.
Will the 2027 Petroleum Law change my existing contract?
MOIT has said that Law No. 10/2026/QH16 observes the principle of non-retroactivity, which ordinarily preserves signed contracts and their fiscal terms, while procedures after 1 March 2027 follow the new law. The transitional provisions and implementing decree should be checked, particularly for extensions, transfers and access to the new incentives.
Does the new Petroleum Law cover carbon capture and offshore wind?
It introduces a framework for carbon capture and storage, shared infrastructure and offshore energy, limited to activities directly linked to petroleum operations. Offshore wind remains electricity generation under Law No. 61/2024/QH15 on Electricity and the marine and investment laws, even where it uses petroleum infrastructure.
Terms you will meet in the documents
| English | Vietnamese | Meaning |
|---|---|---|
| Decommissioning | Thu dọn công trình dầu khí | Removal or making safe of petroleum facilities (Articles 50 to 52). |
| Decommissioning plan | Kế hoạch thu dọn công trình dầu khí | The approved plan with methods, timetable and cost estimate (Article 50). |
| Decommissioning fund | Quỹ bảo đảm nghĩa vụ thu dọn công trình dầu khí | The fund held by Petrovietnam to secure decommissioning (Article 51). |
| First commercial production | Dòng dầu, khí thương mại đầu tiên | The event that starts the one-year deadline for the fund. |
| Research fund | Quỹ nghiên cứu khoa học | The contractual commitment to fund research, a local-content term. |
| Carbon capture and storage | Thu giữ và lưu trữ carbon | Capture and storage of carbon dioxide, covered by the 2027 law where linked to petroleum operations. |
| Post-closure responsibility | Trách nhiệm sau đóng mỏ | Obligations continuing after a field is closed, introduced by the 2027 law. |
| Flaring and venting | Đốt bỏ và xả khí | Burning or releasing gas, restricted by Article 49. |
Related in this guide
Related investor FAQs
- What decommissioning and local-content duties does a petroleum contractor have?
- Who regulates oil and gas, and what is Petrovietnam's role?
- How long does a petroleum contract last, and can it be extended?
- What is the process for investing in energy and power projects?
- What laws govern minerals, mining, oil and gas in Vietnam?
Official sources
- National Legal Database (vbpl.vn): Law No. 12/2022/QH15, Articles 30, 49 to 52 and 59; Decree No. 45/2023/ND-CP, Articles 39 to 44 and 51 to 55
- National Legal Database (vbpl.vn): Law No. 10/2026/QH16 on Petroleum (effective 1 March 2027)
- Ministry of Industry and Trade (briefing on Law No. 10/2026/QH16; draft implementing decree)
- Vietnam National Industry - Energy Group (Petrovietnam): decommissioning fund management
Have a question about your own situation?
Ask Be Vietnam Wise's Lawbot, the AI legal-information chatbot. It checks official Vietnamese sources and points you to the governing law. If you need assistance with your current project or have any enquiries about doing business in Vietnam, please contact us.
Ask Lawbot about thisOpen in the appContact usThis page gives legal and tax information, not legal advice. Rates, thresholds and procedures change; the content is reviewed against official sources, but you should confirm anything important with the relevant authority or a lawyer licensed to provide legal services in Vietnam before you act.