Building permits and the Kigali Master Plan: master plans under the Land Law, zoning and change of use, the Kubaka permit system, permit types and fees, occupancy permits, environmental assessment, liability of construction professionals and the sanctions for building outside the rules

Reviewed · Prepared by a commercial lawyer with over 30 years' international experience · Legal and tax information, not legal advice · How we check · Open in the app

Download chapter 5 as a PDF

What you need to know

The planning hierarchy: from the national plan to the plot

What an investor may build on a Rwandan plot is decided by plans before it is decided by permits. Chapter V of Law N° 27/2021 of 10/06/2021 governing land (the Land Law) builds a hierarchy of land use and development master plans. The national plan is adopted by the Cabinet and established by Presidential Order (Articles 58 and 59); it was established by Presidential Order N° 038/01 of 20/05/2022, published in Official Gazette n° 21 Bis of 23/05/2022. The City of Kigali plan and each District plan are established by an Order of the Minister in charge of economic planning, so the Ministry of Finance and Economic Planning (MINECOFIN) gazettes them one by one; Ministerial Order no 005/24/10/TC of 22/08/2024, establishing the plan of Huye District, is an example. The council of the City of Kigali or of the District then adopts the detailed plan of plots and sites that implements the higher plans (Article 58). Each plan must comply with the plan above it (Article 60).

Article 61 makes the plan binding on everyone who uses land, and it carries a sanction that investors should keep in mind: a permit related to land use that contradicts the master plan is "null and void and has no effects irrespective of any kind of prescription". A building permit issued in error therefore does not protect the holder. The National Land Authority (NLA), as the institution in charge of land use and management, monitors compliance (Article 62), and the City of Kigali and the Districts monitor land use on the ground and may impose administrative fines (Articles 67 and 77). A change of land use must be consistent with the master plan and approved by the NLA (Article 63), and is not a matter the investor and the local authority can settle between themselves. The tenure rules that sit beneath the plans are in The Land Law and land tenure.

The Kigali Master Plan 2050 and conditional uses

The City of Kigali launched its revised Master Plan 2050 on 4 September 2020. It groups land into nine land-use areas, reduced the commercial zones from nine to three and the residential zones from seven to five, introduced overlay zones and allowed more mixed use in the central business district. The zoning maps are published on the City's master plan portal and WebGIS service, and the zoning of a plot can be read against its Unique Parcel Identifier (UPI) through the land and permit systems. District plans outside Kigali are being gazetted by MINECOFIN order, so the instrument that governs a site outside the capital may be recent and should be read in its gazetted form.

Some uses are neither permitted nor prohibited in a zone but may be allowed on conditions, such as a shop in a residential area or a school that meets parking and noise standards. MININFRA suspended the issue of construction permits involving conditional land use and overlay zones in 2025, citing malpractice, until a proper framework is developed; The New Times reported the suspension in August 2025 and quoted experts as saying that projects already permitted should remain unaffected. As at 10 October 2026 no replacement framework had been published. A project that depends on a conditional use should therefore be treated as unpermittable for now, and a site should be chosen where the intended use is permitted outright.

The National Urbanisation Policy launched on 29 April 2025 sets the direction for the next plans: four pillars of coordination, densification, liveability and economic growth, and an urbanisation target of 70% by 2050 under Vision 2050. Densification matters to investors in two ways: plans increasingly favour taller and mixed-use buildings in serviced areas, and serviced land left idle in those areas is exposed to the termination rules described in Expropriation and compensation.

Law N° 10/2012: when a permit is needed

Law N° 10/2012 of 02/05/2012 governing urban planning and building in Rwanda, published in the Official Gazette n° Special of 30 May 2012, is the building statute. Article 83 requires a building permit for all buildings except temporary buildings that may be removed at any time without compensation and specific buildings designed for national defence. Article 84 adds that works exempt from a permit must still be notified in writing to the Mayor of the District, and that the exemption does not release the owner from national rules on urban planning, building, security and hygiene. Article 85 leaves the conditions and procedure to an Order of the Minister in charge of urban planning and building; the current orders are Ministerial Order N° 02/CAB.M/019 of 15/04/2019 on building categories and permits and Ministerial Order N° 03/CAB.M/019 of 15/04/2019 on urban planning and building regulations, which MININFRA lists with the Urban Planning Code, the Building Code and the Green Building Minimum Compliance System. Press reports describe the 2019 categories order as requiring permits for most building activities outside categories 1 and 6; the guide has not been able to read its text, so the category of a specific project should be confirmed on Kubaka before design work starts.

Two further rules are often missed. Under Article 29 an approved execution plan is cancelled if works have not started two years after its approval, although the promoter may obtain an extension of up to six months on request with reasonable grounds. Under Article 87, once a building is completed the owner may not occupy it before obtaining an occupancy permit from the competent authority. The occupancy permit is also one of the documents the registrar requires before converting a lease into freehold under the 2022 freehold Ministerial Order, so an owner who never obtains it closes that door as well. The Rwanda Housing Authority (RHA) supervises building operations nationally (Article 86).

Kubaka: how applications run in 2026

On 29 April 2025 MININFRA launched Kubaka, a "zero trip" online building permit platform that replaced the Building Permit Management Information System (BPMIS) in use since 2016. Applicants file, pay and track applications online, and the platform draws on other government systems instead of asking for paper copies. The New Times, reporting on 23 April 2026, listed the services on Kubaka as new construction permits, inspection notices, renewals, demolition approvals, occupancy permits, temporary structure authorisations, project modifications, change of building use, refurbishment with or without structural changes, and fence permits, and described links to the Land Administration Information System (LAIS) for ownership and zoning, the National Identification Agency for identity, the Rwanda Revenue Authority (RRA) for tax status, the Rwanda Development Board (RDB) for environmental impact assessment certificates, the engineers' and architects' professional bodies (IER and RIA) for licences, and IremboPay for payment.

Processing times are not fixed in any text the guide has seen. Reports at the launch referred to 21 days in Kigali and 30 days in the Districts, and to construction permits valid for one year and renewable; one Kigali homeowner quoted in April 2026 received his permit in 23 days. Treat these as working assumptions, not entitlements, and build in time for corrections: the platform checks the land record and the zoning automatically, so an unregistered transfer, an unpaid tax or a use that does not match the plot plan will stop the file at the start. Delays also occur: The New Times reported on 8 October 2026 that some Kigali applications had taken more than 113 days because of backlogs, which Members of Parliament raised in September 2025. The same report described a permit transfer system introduced by the Rwanda Housing Authority in September 2026, under which the buyer of land that already carries an approved construction permit can take the permit over once the land transfer is complete, provided the approved project is unchanged and the seller makes the approved designs available; otherwise a fresh application is needed. No published instrument setting out this system had been located at 10 October 2026, so a buyer relying on it should confirm the transfer on Kubaka before completion.

Fees: Presidential Order nº 075/01

Building permit fees are fixed by Article 13 of Presidential Order nº 075/01 of 04/12/2023 determining fees levied on services and certificates delivered by decentralised entities (Official Gazette n° Special BIS of 05/12/2023). The fee depends only on the floor area: RWF 20,000 up to 100 m², RWF 100,000 above 100 m² up to 200 m², RWF 150,000 above 200 m² up to 500 m², and RWF 200,000 above 500 m². The same rates apply to the renewal of a building permit and to an authorisation to change the purpose stated in the application. Article 26 exempts from fees the authorisation to renovate or rehabilitate a building, the authorisation to build a fence and a building permit in a rural village, as well as the transfer of ownership of immovable property and the certificate of land registration.

The permit fee is small beside the other costs of building. The larger figures are the professional fees, the environmental assessment, the land tax and immovable property tax that start to run on the plot and the completed building (Land tax, property tax and transfer costs), and the cost of delay if the application is refused for a zoning or title defect.

Environmental assessment and State land

Ministerial Order No 001/2019 of 15/04/2019 lists the projects that need an environmental impact assessment, and the environmental and social impact assessment certificate is obtained through the RDB One Stop Centre; Kubaka checks the certificate electronically. RDB's service charter, as republished in March 2026, gives service standards of 15 days for an EIA clearance and 45 days for an EIA certificate, so the assessment usually sits on the critical path ahead of the building permit. For a project on State land the order is reversed: under Article 12 of Prime Minister's Order N° 008/03 of 03/07/2022, the Minister in charge of land requires an environmental impact assessment before the land is allocated, after checking the master plan, availability and suitability of the land. An investor seeking State land should therefore commission the assessment before it has a site agreement, not after (How foreign investors access land).

Construction professionals, liability and insurance

Law N° 10/2012 treats the architect, the civil engineer, the contractor and any technician with a contract with the owner as construction professionals (Article 31). The architect is responsible for design and for conformity with regulations and development plans, the civil engineer for structural design, stability and technical compliance, and each assumes ten years' liability for works executed from the date of final acceptance (Articles 32 and 33). The contractor executes the works under their technical supervision (Article 34), furnishes a performance bond that it recovers one year after provisional acceptance (Article 35), insures the construction site against all risks when it opens (Article 41) and carries liability insurance for damage resulting from its actions (Article 42). Technical supervision by an approved supervising office is compulsory for complex commercial or industrial buildings, buildings for public use and other buildings presenting specific risks (Article 39).

A foreign contractor or design firm must hold the professional licences that Kubaka checks, and the Chamber of Deputies adopted a new law on construction professions on 24 July 2025; its publication in the Official Gazette had not been confirmed when this guide was prepared. Construction contracts should mirror the statutory regime: final acceptance dates, the ten-year liability, insurance certificates and the release of the performance bond. Contract drafting generally is covered in Commercial contracts in Rwanda.

Sanctions and enforcement

Two sets of sanctions apply. Under the Land Law, failure to comply with the master plan is a fault punished by an administrative fine of RWF 1,000,000 to RWF 3,000,000 (Article 76), multiplied by ten where the offender is a company, a cooperative or an organisation with legal personality (Article 78); the person who carried out the works must also remove them or pay for their removal. Under Law N° 10/2012, faults are recorded by RHA staff with judicial police powers (Article 90), and building without the required authorisation is punished by an administrative fine of RWF 50,000 to RWF 1,000,000, rising to RWF 2,000,000 to RWF 10,000,000 for works on a non-residential building, a public building or a specific building (Article 91). For a foreign-owned company building offices or a factory, the realistic exposure is therefore a fine of up to RWF 30,000,000 for a plan breach plus up to RWF 10,000,000 for unpermitted works, before demolition costs and the loss of the building.

Building in Rwanda: the instruments and the numbers

ItemRuleSource
National master planAdopted by Cabinet; established by Presidential OrderLand Law Arts 58-59; PO N° 038/01 of 20/05/2022
Kigali and District plansOrder of the Minister in charge of economic planning; detailed plot plans by the councilLand Law Arts 58-59
Permit contrary to the planNull and void, whatever the time elapsedLand Law Art 61
Change of land useMust fit the plan; approved by the NLALand Law Art 63
Building permitRequired for all buildings except removable temporary and defence buildingsLaw N° 10/2012 Art 83
Exempt worksWritten notification to the District MayorLaw N° 10/2012 Art 84
Lapse of approvalCancelled if works not started in 2 years; one extension of up to 6 monthsLaw N° 10/2012 Art 29
OccupancyNo occupation before an occupancy permitLaw N° 10/2012 Art 87
Permit feeRWF 20,000 / 100,000 / 150,000 / 200,000 by floor area (100, 200, 500 m² bands)PO nº 075/01 Art 13
Professional liabilityArchitect and civil engineer: 10 years from final acceptanceLaw N° 10/2012 Arts 32-33
Plan breach fineRWF 1,000,000-3,000,000; x10 for companiesLand Law Arts 76, 78
Unpermitted works fineRWF 50,000-1,000,000; RWF 2,000,000-10,000,000 for non-residential, public or specific buildingsLaw N° 10/2012 Art 91

From plot to occupancy: the permit sequence

  1. Read the zoning before you commitObtain the plot's UPI and read its zoning and permitted uses against the gazetted City or District plan and the detailed plot plan; reject any use that depends on a conditional use or overlay permit while the 2025 suspension lasts.
  2. Clear the titleConfirm that the land is registered in the developer's name, that any transfer has been registered (a transfer is valid only on registration under Article 24 of the Land Law), and that taxes and mortgages are in order; Kubaka reads the land record. See Land registration, titles and due diligence.
  3. Environmental assessmentCheck whether the project is listed in Ministerial Order No 001/2019 and, if so, obtain the certificate through the RDB One Stop Centre before filing.
  4. Design by licensed professionalsAppoint an architect and a civil engineer licensed by their professional bodies, prepare drawings to the Building Code and the green building minimum standards, and appoint a supervising office where Article 39 requires one.
  5. File and pay on KubakaSubmit the application online, pay the Article 13 fee through IremboPay and answer queries promptly; reported processing is about 21 days in Kigali and 30 days elsewhere.
  6. Build within the time limitsStart works within two years of approval (Article 29), insure the site (Article 41), keep the permit renewed and apply for a modification before changing the design or use.
  7. Occupancy permitAfter completion, apply on Kubaka for the occupancy permit and do not occupy or let the building until it is issued (Article 87).

Decision guide

Can I build what I plan on this plot?

A first screen for an investor choosing or acquiring a site. The answer is a starting point for the architect and the NLA, not a permit.

  1. Is the intended use permitted outright in the plot's zone under the gazetted plan and the detailed plot plan?
    YesContinue to Q2.
    NoIf the use is only conditional or depends on an overlay, assume no permit can be issued under the 2025 suspension; if it is prohibited, a change of land use needs NLA approval consistent with the plan (Article 63), which is not assured. Choose another site or redesign.
  2. Is the land registered in the developer's name, free of caveats and with taxes paid?
    YesContinue to Q3.
    NoRegister the transfer and clear arrears first; Kubaka checks the land record by UPI and will stop the application.
  3. Is the project on the environmental impact assessment list in Ministerial Order No 001/2019?
    YesObtain the certificate through the RDB One Stop Centre before filing on Kubaka.
    NoFile on Kubaka with the licensed professionals' drawings and the Article 13 fee.
  4. Will works start within two years of approval?
    YesProceed, and diarise the occupancy permit before any occupation or letting.
    NoPlan for the six-month extension under Article 29 or a fresh approval, and remember that serviced land left unexploited for five years can lose its contract.

Worked example

A 1,200 m² office building on a Kigali plot

A Rwandan subsidiary of a Kenyan group holds a registered 49-year emphyteutic lease of a 2,000 m² plot zoned commercial in a Kigali sub-urban area and plans a four-storey office building with 1,200 m² of floor area. All figures except the statutory fees and fines are illustrative.

Zoning checkOffices are permitted outright in the zone; no conditional use is needed, so the 2025 suspension does not apply.
Environmental assessmentAssumed not listed in Ministerial Order No 001/2019 for a building of this size; the architect confirms against the list before filing.
Permit feeFloor area above 500 m², so RWF 200,000 under Article 13 of Presidential Order nº 075/01. A later change of the building's purpose would cost another RWF 200,000.
Land tax while buildingIllustrative council rate of RWF 70 per m² within the Kigali sub-urban band of RWF 50-70 for non-residential land: 2,000 m² x RWF 70 = RWF 140,000 a year.
TimelineKubaka approval in about 3-4 weeks (illustrative); works must start within two years; occupancy permit applied for on completion in month 20.
If the developer had built without a permitFine of RWF 2,000,000 to RWF 10,000,000 for a non-residential building under Article 91 of Law N° 10/2012, plus regularisation or demolition.
If the building breached the plan (for example an extra storey beyond the zone limit)Fine of RWF 1,000,000 to RWF 3,000,000 x 10 = RWF 10,000,000 to RWF 30,000,000 for a company, and removal of the non-compliant works at its cost.

The statutory permit fee is a fraction of one per cent of the project cost; the real risks are zoning, title and time.

Occupying or letting the offices before the occupancy permit breaches Article 87 and undermines the lease to the tenants (see section 5.6).

Questions investors ask

Who issues building permits in Rwanda?

Building permits are applied for online on Kubaka, the MININFRA platform launched on 29 April 2025, and are processed by the City of Kigali or the District One Stop Centre where the plot lies. The Rwanda Housing Authority supervises building operations nationally under Article 86 of Law N° 10/2012, and the NLA approves any change of land use.

How much does a building permit cost in Rwanda?

Article 13 of Presidential Order nº 075/01 of 04/12/2023 sets the fee by floor area: RWF 20,000 up to 100 m², RWF 100,000 up to 200 m², RWF 150,000 up to 500 m² and RWF 200,000 above 500 m². Renewals and changes of purpose cost the same; renovation, rehabilitation, fence and rural village permits are exempt.

Can I occupy a building before I get the occupancy permit?

No. Article 87 of Law N° 10/2012 provides that the owner of a completed building may not occupy it before obtaining an occupancy permit from the competent authority. The permit is also required before a registered lease can be converted into freehold, so it should be obtained as soon as works are complete.

Does a building permit protect me if the project breaches the master plan?

No. Article 61 of the Land Law declares any land use permit granted in contradiction with the master plan null and void, whatever time has passed. The developer remains exposed to fines of RWF 1,000,000 to RWF 3,000,000, multiplied by ten for a company, and to removal of the works under Articles 76 and 78.

Can I get a permit for a conditional use, such as a shop in a residential zone?

Not at present. MININFRA suspended permits involving conditional land use and overlay zones in 2025, citing malpractice, until a proper framework exists, and none had been published by 10 October 2026. Choose a site where the use is permitted outright, or treat the project as dependent on a future framework.

How long does a building approval last?

Article 29 of Law N° 10/2012 cancels an approved execution plan if works have not started within two years of approval, with one extension of up to six months on request. Reports on Kubaka describe construction permits as valid for one year and renewable at the Article 13 rates, so long projects need renewals diarised.

Terms you will meet in the documents

EnglishKinyarwandaFrenchMeaning
Building permituruhushya rwo kubakaautorisation de bâtirThe authorisation required before building under Article 83 of Law N° 10/2012; fees under Article 13 of Presidential Order nº 075/01.
Occupancy permituruhushya rwo gukoresha inyubakopermis d'occupationThe permit without which a completed building may not be occupied (Article 87 of Law N° 10/2012).
Demolition permituruhushya rwo gusenyapermis de démolirThe permit for demolition works under Chapter V of Law N° 10/2012.
Land use and development master planigishushanyo mbonera cy'imikoreshereze n'imitunganyirize by'ubutakaschéma directeur d'utilisation et d'aménagement des terresThe binding national, City or District plan that fixes permitted land uses (Articles 54 to 63 of the Land Law).
Real estate development—promotion immobilièreOperations of preparing plots and building for others, authorised on conditions set by Prime Minister's Order (Article 30 of Law N° 10/2012).
Owner of the works—maître de l'ouvrageThe person for whom the building is built, who applies for the permits and accepts the works.
Performance bond—garantie de bonne finThe contractor's guarantee covering defects, recovered one year after provisional acceptance (Article 35 of Law N° 10/2012).
Technical supervising office—bureau de contrôle techniqueAn approved firm whose supervision is compulsory for complex commercial, industrial and public buildings (Articles 38 to 40 of Law N° 10/2012).
Next in this chapter · 5.6Commercial leases, offices and housingHow offices, warehouses and homes are rented in Rwanda: the contract and land law rules, why rent should be priced in Rwandan francs, the tax on rent, condominium units and the incentives for affordable housing.Continue →

Related in this guide

Related investor FAQs

Official sources

Have a question about your own situation?

Ask Be Rwanda Wise's Rwandabot, the AI legal-information chatbot. It checks official Rwandan sources and points you to the governing law, or read how to find and check a Rwandan advocate.

Ask Rwandabot about thisOpen in the appFind a lawyer

This page gives legal and tax information, not legal advice. Rates, thresholds and procedures change; the content is reviewed against official sources, but you should confirm anything important with the relevant authority or an advocate registered with the Rwanda Bar Association before you act. Laws are published in Kinyarwanda, English and French in the Official Gazette; check the official text before relying on a translation.