Rooftop solar explained

How a rooftop system is designed, installed and connected, which inverter to choose, and the paperwork and payments that follow.

Looking for a specific answer? See Rooftop solar, grid connection and VAT and G98 and G99 explained.

Start here

The short version

  1. An MCS-certified installer surveys your roof and designs a system. For a typical home that is about 4.5 kWp, around 12 panels.
  2. You get a written quote with an estimate of what it will generate. If you sign at home, you usually have 14 days to change your mind.
  3. Installation is often done in a day or two, with scaffolding. The inverter usually goes in the loft or garage.
  4. The installer tests the system, tells your network operator and gives you the paperwork, including the MCS certificate.
  5. With the MCS certificate you can sign up to a Smart Export Guarantee tariff and be paid for the electricity you export.
Getting rooftop solar, step by stepSurvey and design; written quote; contract with a cooling-off period; installation; testing and switch-on; paperwork and network notification; applying for export payments.1Survey and designThe installer checks your roof, shading, wiringand fuse box.2Written quoteItemised prices and a performance estimate foryour roof.3ContractSigned at home? You usually have 14 days to cancel.4InstallationScaffolding, panels, inverter and wiring: often aday or two.5Testing and switch-onThe system is commissioned and tested.6PaperworkMCS and electrical certificates, warranties,network notified.7Export paymentsApply to a supplier's SEG tariff with your MCScertificate.
From first visit to export payments.

Layer 2

In more detail

Sizing, inverters, the grid, the rules and what you should be given at the end.

How big a system?

The size depends on your roof space, which way it faces, your budget and how much electricity you use. The Energy Saving Trust gives about 4.5 kWp, around 12 panels, as typical, costing around £7,600. As a rough guide, a well-sited UK system makes around 750 to 1,100 kWh a year for each kWp. Ofgem’s figure for a typical home’s use is 2,500 kWh a year, but you won’t use all your solar electricity as it is made, so a bigger system mainly means more exported unless you add a battery or use more in the daytime.

Check an installer’s estimate with our solar generation estimator.

Choosing an inverter

String inverters, microinverters and optimisersString inverter: panels wired in series to one central inverter. Microinverters: a small inverter behind each panel, sending AC down from the roof. Optimisers: a small box behind each panel, still feeding one central inverter.String inverterOne central box. Simple and usually cheapest.InverterDC to ACACMicroinvertersOne per panel. Shade on one panel affects only that one.AC to the homePower optimisersOne per panel, plus a central inverter.InverterDC to ACAC
The three common ways of turning the panels’ DC into AC.

The Energy Saving Trust says an inverter usually needs replacing after around 12 years, so check its warranty and budget for it.

Inverter size and the grid

On a normal single-phase supply, a system with an inverter of up to about 3.68 kW can be connected first and then notified to your network operator under G98. A bigger inverter needs the operator’s approval under G99 before it is installed. That is why many systems of around 4 to 5 kWp of panels use an inverter of about 3.6 kW: the panels rarely produce their full rating, so little is lost.

See how inverter size, panel size and the G98 limit fit together with our inverter size checker.

Planning and building rules

In England, rooftop panels on a house are usually permitted development if, on a pitched roof, they are no higher than the highest part of the roof and stick out no more than 200 mm, and, on a flat roof, they are no more than 600 mm above the highest part. Listed buildings, conservation areas and Article 4 areas are different. Wales, Scotland and Northern Ireland have their own rules. The electrical work must meet building regulations, and the installer should check that your roof can take the extra weight. See Do I need permission?

Paperwork you should be given

The Renewable Energy Consumer Code, which many MCS installers follow, requires members to hand over:

These must not be held back until you have paid in full. Also keep confirmation that your network operator has been notified, the warranties for the panels, inverter and any battery, and the workmanship guarantee. See Choosing a good installer.

Being paid for exports

Under the Smart Export Guarantee, suppliers in Great Britain with at least 150,000 domestic customers must offer a tariff for the electricity you export, and the installation needs an MCS (or equivalent) certificate. Rates vary, so compare them. Northern Ireland is different. See Tariffs and export payments.

Insurance and your mortgage

Tell your home insurer before the panels go up, and check your mortgage terms, as lenders often expect to be told. Be very careful with “free panels” offered in return for leasing your roof: it is a long-term, legally binding lease, and lenders expect to be asked for consent. Take independent legal advice before signing one.

Key words

Inverter
The box that turns DC into AC. String, micro and hybrid are the main types.
G98 / G99
The two routes for connecting generation to the grid in Great Britain: notify afterwards, or apply first.
MCS certificate
Proof the system was installed to the scheme’s standards. Usually needed for export payments.
Commissioning
Testing and switching the system on, and recording the results.
Layer 3For the technically mindedWiring, MPPT, DC to AC ratio, G98, G99 and export limits, standards
Single-line diagram of a grid-connected solar systemFrom the top: solar panels, DC isolator, inverter, AC isolator, generation meter, consumer unit, smart meter, cut-out and main fuse, and the local network. The section from the panels to the inverter carries direct current; everything after the inverter carries alternating current.How the parts connect (simplified)Solar panels (the array)panels wired in series as “strings”DC isolatorswitch to cut the panels’ DC supplyInverterDC to AC; tracks the best operating pointAC isolatorswitch to isolate the inverterGeneration meter (often fitted)records total solar generatedConsumer unit (fuse box)solar on its own protected circuitSmart metermeasures import and exportCut-out and main fusethe network operator’s equipmentThe local networkyour network operator’s cablesDC sideAC side
A simplified single-line diagram of a grid-connected system.

Strings and MPPT

Panels in series add their voltages, so a string can run at several hundred volts DC. Inverters track the best operating point of each string (maximum power point tracking, MPPT). Panels facing different ways, or with different shading, are usually put on separate MPPT inputs. Check the design keeps string voltages inside the inverter’s limits in cold weather, when panel voltage rises.

DC to AC ratio

The panels’ total rating divided by the inverter’s AC rating. Ratios a little above 1 are common in the UK, because panels seldom reach their rated output; the energy lost to clipping is small until the ratio gets well above 1.2 to 1.3 on a south-facing roof, and smaller for east-west arrays, whose output is spread through the day.

G98, G99 and export limitation

Engineering Recommendation G98 covers type-tested generation up to 16 amps per phase: about 3.68 kW single-phase, or up to 11.04 kW across three phases. The installer submits Form B within 28 days of commissioning, quoting the inverter’s reference on the Energy Networks Association’s Type Test Register. G99 applies above that, and to storage that takes the total over the limit, with an application before installation. The network operator may agree a larger inverter with a limit on export.

Standards

MCS-certified installers work to the MCS solar PV installation standard (MIS 3002), and to MIS 3012 for batteries. They must belong to a consumer code approved by the Chartered Trading Standards Institute (RECC or HIES), which gives access to alternative dispute resolution.

Power cuts

Grid-connected inverters disconnect when the grid fails, to protect people working on the network, so a standard system gives no power in a power cut. Backup needs a system designed for it, with automatic isolation from the grid.

Frequently asked questions

What is the difference between G98 and G99?

They are the two main network connection routes in Great Britain. G98 covers small type-tested generators up to 16 amps per phase, which is about 3.68 kW on a single-phase supply: you connect and then notify your network operator, normally within 28 days. G99 applies above that level and needs the operator's permission before you install.

Full answer with sources

Do I have to tell my network operator about rooftop solar?

Yes. Your installer normally does this for you: a G98 Form B within 28 days of installation for small systems, or a G99 application before installing for larger ones. Batteries count too. Ask your installer for a copy of the notification and keep it with your paperwork.

Full answer with sources

Do I have to use an MCS-certified installer?

If you want export payments, effectively yes. Under the scheme rules, solar of up to 50 kW must be installed by a certified installer and certified under MCS or an equivalent scheme; without that, a supplier does not have to pay you under the SEG, although some may choose to. MCS certification also brings consumer protection, because MCS installers must belong to a consumer code (RECC or HIES).

Full answer with sources

Is there VAT on solar panels?

For most homes, installation is currently zero-rated. A 0% VAT rate applies to the installation of energy-saving materials, including solar panels, in residential accommodation in Great Britain from 1 April 2022 and in Northern Ireland from 1 May 2023, until 31 March 2027. The reduced 5% rate is scheduled to return after that unless the government extends the relief. The relief is tied to installation, not to materials alone.

Full answer with sources

When is G98 enough for my solar system?

G98 covers type-tested generators up to 16 amps per phase, about 3.68 kW on a single-phase supply. On a three-phase supply you can use G98 with up to 3.68 kW on each phase, or up to 11.04 kW as a single three-phase system. You connect first, and your installer notifies the network operator afterwards.

Full answer with sources

When do I need G99 instead?

G99 applies to installations above 16 amps per phase (3.68 kW), or that do not meet the G98 requirements, and it covers generation and energy storage together. You must apply to your network operator and get its agreement before installing. Smaller G99 installations have a simplified process, and network operators may have their own forms.

Full answer with sources

Do I need to tell my home insurer before installing solar panels?

You should. Insurers such as LV= say fitting panels is a major change to your home that could affect your cover and premium, and the Energy Saving Trust advises contacting your buildings and contents insurer before installing. For plug-in solar the government specification makes the user responsible for checking whether it affects their insurance.

Full answer with sources

Do I need my mortgage lender's permission to fit solar panels?

Check your mortgage terms. A fixed installation can count as an alteration to the property, so lenders often expect to be told or asked first, and some will not proceed unless the installation is MCS-certified. Requirements vary by lender, so ask yours before you sign an installation contract.

Full answer with sources

Got a quote? Tell SolarBot the system size and inverter and it will explain what the figures mean.

Ask SolarBot

Official sources

How we check these pages · Recent changes · All solar FAQs · Glossary

Written 2 October 2026. General information, not legal, electrical or financial advice. Confirm current rules before you buy or connect anything.